Ford Livonia Transmission: South Chiller Building

Project Details


Location: Livonia, Michigan
Owner: Ford Motor Company
Delivery Method: Construction Commodity Management
Project Value: $2,000,000

Architect/Engineer: SSOE
Size: 5,000 SF

Construction Commodity Manager

Stenco was the general contractor for the construction of a 5,000 SF Chiller Building addition to the cooling tower structural steel on the south side of the Ford Livonia Transmission Plant.

This nine month project consisted of:

  • Piping work
  • Electrical grounding
  • Concrete foundations and asphalt paving
  • Structural steel fabrication and erection
  • Siding, roofing, and gutter work

 

View Additional Project Highlights Below:

August 2017 Stenco Report

Please enjoy the August issue of The Stenco Report! This issue highlights our work at St. Mary Mercy Hospital in Livonia, Michigan.  Download the August 2017 Stenco Report

October 2016 Stenco Report

Please enjoy the October issue of The Stenco Report! This issue highlights our work at the new Michigan Veteran's Foundation. Download the October 2016 Stenco Report

May 2016 Stenco Report

Please enjoy the May issue of The Stenco Report! This issue highlights our Ford Land Renovations, our own office renovations, and the launch of THIS website!

December 2015 Stenco Report

Please enjoy the December issue of The Stenco Report! This issue highlights our work at VA Ann Arbor Hospital, Ford Livonia Transmission, and University of Michigan Dearborn. Download The December 2015 Stenco Report
Page: 1234 - All
Looking for a top level contractor for your next big interior buildout?
Trust Stenco to deliver the highest in quality and customer satisfaction - on time and on budget.
Request A Bid