Project Details


Location: Livonia, Michigan
Owner: Ford Motor Company
Delivery Method: Construction Commodity Management
Project Value: $2,000,000

Architect/Engineer: SSOE
Size: 5,000 SF

Construction Commodity Manager

Stenco was the general contractor for the construction of a 5,000 SF Chiller Building addition to the cooling tower structural steel on the south side of the Ford Livonia Transmission Plant.

This nine month project consisted of:

  • Piping work
  • Electrical grounding
  • Concrete foundations and asphalt paving
  • Structural steel fabrication and erection
  • Siding, roofing, and gutter work

 

View Additional Project Highlights Below:

Stenco Report Newsletter - Fall 2021

The Fall 2021 issue of the Stenco Report newsletter features University of Michigan's new dance building, Toyota's Production Engineering and Manufacturing Center and renovations to two Veterans Affairs Medical Centers.

Stenco Report Spring 2019

In our Spring 2019 issue of the Stenco Report, we feature our work for Nissan in Smyrna, TN, the University of Michigan's new Multicultural Center, and a renovation at a Veterans Affairs Medical Center. Download the Spring...
Page: 1234 - All
Looking for a top level contractor for your next big interior buildout?
Trust Stenco to deliver the highest in quality and customer satisfaction - on time and on budget.
Request A Bid