Nissan Motor Company

Stamping Bay 8 Addition

Location: Smyrna, Tennessee
Owner: Nissan Motor Company
Project Value: $27,000,000

Stenco was selected for the Nissan Stamping Plant Bay 8 Addition project. This critical building addition added 60,000 SF and a 150-foot-long stamping press pit to the Smyrna Vehicle Assembly Plant.

Project scope included:

  • Relocation of multiple utilities, including underground storm piping, fire lines, domestic water, natural gas and sanitary sewers
  • Rock blasting for utility excavation and relocation, digging up to 25 feet deep
  • Relocation of the main access ring road and a railroad
  • More than 3,100 CY of concrete for the foundations and press pit

Stenco was selected for this project due to their self perform capabilities and reputation for safe and quality work.

Stenco Report Newsletter - Fall 2021

The Fall 2021 issue of the Stenco Report newsletter features University of Michigan's new dance building, Toyota's Production Engineering and Manufacturing Center and renovations to two Veterans Affairs Medical Centers.

Stenco Report Spring 2019

In our Spring 2019 issue of the Stenco Report, we feature our work for Nissan in Smyrna, TN, the University of Michigan's new Multicultural Center, and a renovation at a Veterans Affairs Medical Center. Download the Spring...