FCA SHAP Body Shop: Concrete Foundations, Pits, Grade Beam

Project Details


Location: Sterling Heights, Michigan
Owner: Chrysler Corporation
Delivery Method: Self Perform

Project Value: $4,000,000
Architect/Engineer: NSA Architects
Year Completed: 2013

 

Self Perform

Concrete foundations, pits, and grade beam associated with construction
of a 1,000,000 SF Body Shop addition at the Sterling Heights Assembly Plant. The project included 4,100 LF gradewall, 29 truck docks, 7 pits, 60,000 SOG, grouting over 300 column bases, and the excavation and backfill of 5,100 LF of fire line.

 

View Additional Project Highlights Below:

Winter 2018 Stenco Report

In our Winter 2018 issue of the Stenco Report, we feature the Ford Motor Company Vehicle Performance & Electrification Center (VPEC) project, highlight recent University of Michigan work, showcase our Toyota Motor Manufacturing supplier...

April 2018 Stenco Report

In our April 2018 issue of the Stenco Report, we are celebrating our 20th year in business, talking about our work with DTE Energy and the University of Michigan, and recognizing some outstanding work by our team. Download the...

Stenco Construction Celebrates 20th Anniversary

2018 marks the 20th anniversary for Stenco Construction. These last twenty years have shown notable successes for Stenco Construction, including the company’s growth into one of the largest minority owned businesses (MBE) supplying construction services in southeast Michigan.
Page: 1234 - All
Looking for a top level contractor for your next big interior buildout?
Trust Stenco to deliver the highest in quality and customer satisfaction - on time and on budget.
Request A Bid